Brookfield 2020 Street Improvements Project
  • Project Info
    • F.A.Q.s
  • Project Map
  • Construction Updates
    • General Street Improvements
    • Park Avenue
    • Other Work
  • Notices
    • General Construction Notice
    • Intersection Improvements Notice
  • Photos and Media
  • Contact Us
  • Hancock Engineering
  • Village of Brookfield
2020 Street Improvements Project
Village of Brookfield
An improvement project that will benefit the residents and visitors of the Village of Brookfield.
 NOTE: PLEASE REFER TO THE "CONSTRUCTION UPDATES" TAB FOR UP TO DATE INFORMATION REGARDING THE CONSTRUCTION SCHEDULE FOR THIS PROJECT
Project Background:

The construction season has begun with the following locations planned for improvement:

Park Avenue from Monroe Avenue to 31st Street
Grant Avenue from Maple Avenue to Grand Boulevard
Sunnyside Avenue from Brookfield Avenue to Grand Boulevard
Hollywood Avenue from Brookfield Avenue to Washington Avenue
Woodside Avenue from Parkview Avenue to Washington Avenue
Ridgewood Road from Woodside Avenue to Golf Avenue
Rosemear Avenue from Southview Avenue to Riverside Avenue
Hollywood Avenue from Southview Avenue to Riverside Avenue
Woodside Avenue from Southview Avenue to Wasubansee Road
Greenview Avenue from McCormick Avenue to Woodside Avenue
Grand Boulevard and Prairie Avenue Intersection
Concrete Pavement Patching throughout Village
Asphalt Patching throughout Village        

Generally, the contractor first begins with underground work (sewer improvements), followed by concrete removal and replacement, and then improving the pavements. 

It is anticipated that the work on the project will be substantially completed by October 1st.  

An up to date construction schedule and project status can be found on the “Construction Updates“ tab.



Project Scope:

General Street Improvements (includes all streets listed above with the exception of Park Avenue)
NOTE: See updates for this portion of the project on the "General Street Improvements" option under the "Construction Updates" tab

The pavements on Grant Avenue, Hollywood Avenue (Brookfield Avenue to Washington Avenue), Woodside Avenue (Parkview Avenue to Washington Avenue), Rosemear Avenue, Hollywood Avenue (Southview Avenue to Riverside Avenue), and Woodside Avenue (Southview Avenue to Waubansee Road) will be widened to 25’ E-E and resurfaced. The work to be performed will include the removal and replacement of the curb and gutter, the removal and replacement of sidewalks, driveway aprons, replacement or repair of defective drainage structures, replacement of certain sections of combined sewer, milling of the existing pavement, removal and replacement of deteriorated sections of pavement, installation of hot-mix asphalt binder and surface courses, restoration of disturbed sections of the parkways, and other related work.
The pavements on Sunnyside Avenue and Ridgewood Road will be resurfaced. The work to be performed will include the removal and replacement of deteriorated sections of curb and gutter, the removal and replacement of sidewalks, driveway aprons, replacement or repair of defective drainage structures, replacement of certain sections of combined sewer, milling of the existing pavement, removal and replacement of deteriorated sections of pavement, installation of hot-mix asphalt binder and surface courses, restoration of disturbed sections of the parkways, and other related work.

 
Park Avenue Street Improvements
​
NOTE: See updates for this portion of the project on the "Park Avenue" option under the "Construction Updates" tab

The pavement on Park Avenue will be widened to 25’ E-E and reconstructed. The work to be performed will include the removal and replacement of curb and gutter, sidewalks, driveway aprons, replacement or repair of defective drainage structures, replacement of certain sections of combined sewer, excavation of existing pavement, installation of an aggregate base course with geogrid, hot-mix asphalt binder and hot-mix asphalt surface course, restoration of disturbed sections of the parkways, and other related work.
 
Also included in the work to be performed on Park Avenue is the installation of approximately 2000’ of 8” ductile iron pipe water main to be connected to the existing water mains at Monroe Avenue and 31st Street.


Intersection Improvements at Grand Boulevard and Prairie Avenue
NOTE: See updates for this portion of the project on the "Other Work" option under the "Construction Updates" tab

 
This project will include improvements to the intersection of Grand Boulevard and Prairie Avenue area. The work to be performed will include removal and replacement of curb and gutter, removal and replacement of sidewalks, installation of drainage structures and storm sewer, installation of brick paver cross walks over concrete base course with concrete bands, installation of bump outs to increase landing size, brick sidewalks over concrete base, pavement reconstruction, installation of hot-mix asphalt surface course, and other related work.

 
Asphalt and Concrete Patching

NOTE: See updates for this portion of the project on the "Other Work" option under the "Construction Updates" tab
 
This project will also include concrete pavement and asphalt patching locations outside of the limits of the streets listed above.  These pavement patches are located throughout the Village. The work to be performed will include removal and replacement of curb and gutter, removal and replacement of sidewalks, driveway aprons, repair of defective drainage structures, removal and replacement of deteriorated sections of concrete pavement, installation of hot-mix asphalt surface course, restoration of disturbed sections of the parkways, and other related work.



Traffic Impacts During Construction (North and South Hollywood):

The project will consist of four main phases of work: sewer installation, concrete installation, improvements, and asphalt paving.
 
During the sewer installation phase, the contractor may post “No Parking” signs on certain sections of street where he will be working during the day.  Residents will be allowed to park their vehicles on the street overnight, however; we ask that while the contractor is working adjacent to your house, you have your vehicle moved prior to 7:00 AM to reduce the possibility of accidental damage from the construction machinery.
 
During the concrete installation phase, the contractor will work on one side of the street at a time.  The contractor will post “No Parking” signs on that side of the street.  Overnight on-street parking will be allowed on the opposite side of the concrete work.  We ask that the vehicles parked on the opposite side of the concrete work be moved off street from 7:00 AM to 5:00 PM to reduce the possibility of accidental damage from the construction machinery.  
 
During the pavement improvements phase, the contractor will post “No Parking” signs on an entire street.  Vehicles will have to be moved prior to 7:00 AM on the specified date and the street will remain closed until the entire pavement has been removed and the stone base has been installed. 
 
During the asphalt paving phase, the contractor will post “No Parking” signs on an entire street, and parking will not be permitted from 7:00 AM to 5:00 PM on the specified dates.
 
Parking restrictions for street sweeping will be relaxed within the near vicinity of the project to allow for overflow parking as the project is ongoing. 


Traffic Impacts During Construction (Intersection Improvements):

The Intersection Improvements at Grand Boulevard and Prairie Avenue will have several stages of work that will affect parking availability and through traffic in various ways. Please refer to the "Other Work" section under the "Construction Updates" tab for the latest updates regarding traffic impact and accessibility. 


Garbage Collection :
We do not anticipate that garbage collection will be affected.  However, notice will be given to all affected residents if any changes in service are necessary once work begins.


Picture